Fourth Ave. S, Todd County

2025 roadwork

Begins early June

MnDOT will resurface and improve about one-mile of Hwy 287 (Fourth Ave. S) in Long Prairie, includes pedestrian updates.

2025 roadwork location map on Hwy 287 in Long Prairie
Hwy 287 roadwork location map Hwy 71 (Lake St.) to just east of Ninth St. SE. Select image to enlarge (PNG)

Summary of work

  • Resurface road (mill and overlay asphalt)
  • Update storm drainage, includes underground pipe at First St. S and curb and gutters
  • Upgrade and widen pedestrian sidewalks and approaches
  • Install new pedestrian flasher signals at:
    • Hwy 287 and First St S, west of the elementary school
    • Hwy 287 and Second St S, east of the elementary school to Harmony Park
  • Install new reflective pavement markings
  • Make other repairs as needed

Future impacts

Overall, impacts will be minimal. Most 2025 work to occur while school is out on summer break.

Motorists

  • Lane or shoulder closures, lane shifts, use of flaggers
  • Hwy 287 open to two-way traffic; however, expect changes to access, gravel surfaces and no shoulders
  • Watch for pedestrians crossing Hwy 287, as both sides have homes, churches and parks
  • Detour up to five days to replace pipe and work under Hwy 287 near First St. S
    • Hwy 287 closed between Hwy 71 and Eighth St. S.
      • Detour uses Hwy 71, First Ave. NE and Eighth St. S.

Pedestrians

  • Sidewalk closures, detours
  • Look both ways before crossing the road and stay out of closed areas

Information tentative and subject to change.