About the project

Project Elements
- Pavement reconstruction
- Sidewalk reconstruction
- Storm sewer reconstruction
- Corridor lighting
- Utility improvements
- Tree/brush removal
Project Staging
Disclaimer: Staging information and detour routes are subject to change. Estimated durations and detours are as follows. Project staging and detour maps coming soon.
A truck detour will be used for the duration of the project. Truck traffic will detour onto Roseau County roads 4 and 23. Local traffic can use city streets to avoid the road closure.
Stage 1
Hwy 11 will be closed between the east side of 4th St to west side of Hwy 32 intersection (Approximately 5 weeks)
Work to be completed:
- Install storm sewer on Hwy 11
- Install storm sewer outlet to South Brantch Two Rivers
- Reconstruct Hwy 11
- Sidewalk reconstruction
- Install bases for corridor lighting
Stage 2
Hwy 11 will be closed between the west side of 7th St to the east side of 4th St (Approximately 7 weeks)
Work to be completed:
- Install storm sewer on Hwy 11
- Reconstruct Hwy 11
- Sidewalk reconstruction
- Install bases for corridor lighting

Stay Informed
Stay informed during the project by attending weekly construction meetings and sign up for email updates on the project website.
Nearby Projects
2025: Hwy 11/313 Warroad
2026: Hwy 11 Roseau to Warroad
2028: Hwy 89 Roseau
Work Zone Safety Tips
- Obey posted speed limits
- Drive undistracted
- Move over-Give workers room to safely complete their work.
- Know before you go: www.511mn.org
- Be patient.
- Do the zipper merge
- Avoid making unnecessary lane changes
- Never enter a road blocked with barriers or cones
- Expect work zones to constantly change