Hwy 169—Garrison

Crow Wing County 

2026 roadwork

MnDOT will improve five miles of Hwy 169 from south of Garrison at Crow Wing Co. Rd. 26 to north of Garrison at Pike Ave.; includes city storm sewer, sidewalk and a new roundabout at the busy Hwy 18 intersection.

Latest news

Summary of work

Project location map
Select project location map to enlarge (PNG)

In Garrison

  • Reconstruct Hwy 169 from the north and south city limits, includes adjacent entrances and road approaches
  • Construct a new four-legged roundabout at the intersection of Hwy 169, Hwy 18 and Monroe St.
  • Install new city storm sewer
  • Update or add pedestrian sidewalk and approaches
  • Upgrade lighting

North and south of Garrison

  • Resurface (mill and overlay) from south of Co. Rd. 26 to south of Hwy 18 in Garrison and north of Hwy 18 to Pike Ave., one mile north of Hwy 1811
  • Reconfigure turn lanes at Co. Rd. 26
  • Replace or repair drainage structures
  • Upgrade guardrail

Roundabout design

The single-lane, four-legged roundabout layout concept illustrated at the Hwy 169, Hwy 18 and Monroe St. intersection, includes sidewalks (Updated November 2025).

Urban segment of Hwy 169 in Garrison from the updated preliminary layout
Garrison layout updated November 2025: Image (PNG) or download (PDF)

Future impacts

Spring-fall 2026

Construction will begin after the Fishing Opener on Monday, May 11. Traffic will be detoured most of the season.

Those who travel through the work zone will encounter single-lane traffic with no shoulders, use of alternate entrances, hard closures, flaggers and reduced speeds.

Schedule at a glance

All details are tentative and subject to change once contractor is on board. Weather and materials may also change the schedule.

Dates Work Impacts

Late spring 2026
Prep work:
begins May 11 (after fishing opener)

  • Resurface (mill and pave) the north end of Hwy 169 from Hwy 18 in Garrison to north limits
  • Prepare work areas, includes road widening near Co. Rd. 26 and temporary roundabout at Hwy 169/Hwy 18 intersection in Garrison

Hwy 169 between Hwy 18 and Pike Ave.

  • Road closed and detoured (PNG) via Hwy 18 Garrison, Hwy 6 Bay Lake to Co. Rd. 14/11 Bennettville
  • Local access maintained; however, expect changes and delays

Hwy 169 between Hwy 18 and Co. Rd. 24

  • Expect single-lane traffic, no shoulders and reduced speeds

Summer 2026

Construct: Mid-June - Sept. 7 (Labor Day)

  • Reconstruct Hwy 169 through the city of Garrison, includes: road, entrances, curb/gutter, underground storm sewer and pedestrian facilities
  • Construct roundabout at Hwy 169, Hwy 18 and Monroe St.
  • Update/ repair the St. Alban's Bay historic culvert bridge
  • Reconfigure turn lanes to improve access at Hwy 169 and Co. Rd. 26

Hwy 169 between Hwy 18 and Pike Ave.

  • Open - work complete

Hwy 169 between Hwy 18 and Co. Rd. 24

Local access

  • Temporary roundabout at Hwy 18/169 in Garrison
  • Monroe OR Central St. will be open
  • Single-lane traffic, no shoulders, reduced speeds, lane shifts and flaggers through the work zone

Early Fall 2026
Complete work in Garrison: Begins Sept. 7
( Labor Day)

  • Construct roundabout connections
  • Remove temporary roundabout
  • Continue work between Hwy 18 and Co. Rd. 26

Hwy 169 from Co. Rd. 26 to Hwy 18

  • Intersection closed to all traffic at Hwy 169, Monroe St. and Hwy 18 in Garrison
  • Road closed and detoured (PNG) via Co. Rd. 26, Co. Rd. 8, Hwy 18, Co. Rd. 6 Bay Lake and Co. Rd. 14/11 Bennettville

Local access

  • Access via sidestreets
  • Hwy 169 one lane one-way traffic, no shoulders, reduced speeds, lane shifts and flaggers

Fall
Complete south end work:
October

  • Resurface (reclaim/recycle road surface) from Co. Rd. 26 to south of Garrison (city limits)

Hwy 169 in Garrison

  • New road and roundabout open - work complete

Hwy 169 between Co. Rd. 26 and south limits of Garrison

Local access

  • Hwy 169 south of city limitis: one lane one-way traffic, no shoulders, reduced speeds, lane shifts and flaggers

 

Late Fall

November
Wrap up

  • Complete any remaining work on south end, includes work at the St. Alban's Bay historic culvert
  • Turf establishment may continue in 2027
  • South of Garrison to Co. Rd. 26
  • Lane/shoulder closures, flaggers